User Personas: Admin | Project Manager
Job cost reporting only tells you the truth if the project underneath it is set up correctly. A report cannot calculate a margin without a contract value, cannot cost an hour without a rate template, and cannot group anything sensibly without cost codes.
This article walks through the four things to configure on a project before you rely on its job cost numbers. Do them once, at project setup, and the reporting takes care of itself from then on.
To perform the actions described in this article, you must have the Project Admin - Project Settings - Edit permission. See the Permissions table at the end of this article.
Use the links below to jump to a topic:
- How the Pieces Fit Together
- Enter the Project Contract Value
- Set the Project Rate Template
- Set Up the Project Cost Codes
- Configure the Project Budget
- Check Your Setup
- Permissions
- FAQ
How the Pieces Fit Together
Each setup step feeds a different part of the job cost picture. Skipping one does not produce an error message, it produces a report with a blank or misleading column, which is harder to catch.
Order |
What you set up |
What breaks without it |
1 |
There is no revenue figure to measure costs against, so margin cannot be calculated. | |
2 |
Field hours record as hours but carry no dollar value, so labor cost reads as zero. | |
3 |
Costs land against the wrong buckets, or against a list so long that users pick the wrong one. | |
4 |
Actual costs have nothing to be compared against, so every variance column is meaningless. |
Once the project is configured, you do not re-enter any of this by hand. Budget adjustments flow in through Change Order Requests, and committed costs to labor, materials and production units flow in through Daily Reports and Purchase Orders.
Setup item |
What consumes it |
| Revenue and margin calculations on job cost reporting. | |
| Daily Report crew hours and Change Order Request labor items, which is how hours become dollars. | |
| Every costed document: Change Order Requests, Daily Reports and Purchase Orders. | |
| The budgeted side of every variance comparison, including labor hours and production units. |
Enter the Project Contract Value
The Contract Value is the revenue side of the equation. Job cost reports use it to calculate margins against your committed costs, which accumulate as a byproduct of documenting the purchases and labor performed on the contract.
- Go to the project, then select Project Info under Settings in the slide-out menu
- Select Edit on the action button
- Enter a dollar amount in the Contract Value field
- Select Save
| Enter the contract value even if the number is provisional. A close estimate produces a usable margin, and an empty field produces none at all. Approved Change Order Requests adjust the figure as the job progresses. |
Set the Project Rate Template
Rate Templates are configurable rate structures that turn recorded hours into dollars. They allow crew hours from Daily Reports and labor items from Change Order Requests to populate labor rates on job cost reports.
An Admin configures the Rate Templates available to your company. For guidance on building them, see the Labor Rates Setup article.
- Go to the project, then select Project Info under Settings in the slide-out menu
- Select Edit on the action button
- Choose the desired rate template in the Craft Template field
- Select Save
A Rate Template does nothing until it is assigned to a job. This is the step most often missed, and it is the usual cause of labor hours appearing on a report with no cost attached.
|
Missing labor commitments or labor dollars after entering a Daily Report with timecards?
The usual cause is a missing Labor Class or Rate Template. Blank values in the Labor Class field on the Crew tab of a Daily Report, or in the Timecard Management log, are the first tell. If no Labor Class or Rate Template was assigned when the Daily Reports were entered, the Job Cost Report will not show any committed labor dollars. To correct it:
The Job Cost Report may take a few minutes to reflect the change. |
Set Up the Project Cost Codes
Configuring the project cost code list makes job cost reports more accurate. You can rename cost codes to match how this particular job is bid, and hide the ones with no budgeted activity so they cannot be selected by mistake on Change Order Requests, Daily Reports or Purchase Orders.
An Admin configures the default company cost code list under Company Settings. See the Cost Codes Setup article for guidance.
- Go to the project, then select Cost Codes under Settings in the slide-out menu
- Select Edit on the action button
- To rename a cost code, select it and edit the cost code name
- To change a category, select the Category field on the cost code, then add or remove categories as needed
- To assign or remove a cost code from the project, toggle Use for Project to Yes or No
- Select Save
| Hide the cost codes that do not apply to this project. It simplifies the workflow for your field users and cuts down the risk of somebody selecting the wrong code while creating project documentation, which is far more time consuming to correct after the fact. |
Configure the Project Budget
The budget is what every actual cost gets measured against. You can enter it manually or import it from the provided template. For complete steps and additional guidance, see the Project Budget Setup article.
- Select a project from the project list, then select Budgets under Settings in the slide-out menu
- Follow the steps in one of the two sections below, depending on your preferred method
Enter the Budget Manually
Manual entry suits smaller jobs, or a budget that is still being finalized.
- Select Edit on the action button
- Enter the budgeted values against each cost code
- Select Save
Import the Budget
Importing suits a job that was estimated outside eSUB Fusion, which is the more common case on larger work.
- Select the import option on the action button
- Download the file template
- Fill out the template with your budgeted values
- Upload the completed file
- Review the imported values and correct any that did not map as expected
- Select Save
Check Your Setup
Before you rely on the numbers, confirm the four pieces are in place. Each check takes a few seconds and catches the failure modes that are otherwise easy to miss.
Check |
How the field should look |
| Project Info shows a dollar amount, not a blank field. | |
| Project Info names a template, and the labor classes your crew actually uses appear on it. | |
| The project list contains the codes this job needs and excludes the ones it does not. | |
| Budgeted hours, units and dollars appear against the cost codes you expect. |
A useful final test is to open a job cost report on the project before any real cost has accumulated. The budgeted columns should be populated and the actual columns should be zero. If a budgeted column is unexpectedly empty, the setup step that feeds it was missed.
Permissions
| Permission | What it allows |
| Project Admin - Project Settings - Edit | Edit Project Info, including Contract Value and the rate template, and configure project cost codes and budgets. |
| Company - Labor Classes - General Permissions | Build and edit the Rate Templates that projects draw from. Held by an Admin, not usually by a project user. |
| Analytics - Labor Reports - View | View the labor reporting that this setup feeds. |
If a user cannot see an option described in this article, review their permissions. Admins manage these from User Permissions.
FAQ
Does the setup order actually matter?
For the most part, yes. Cost codes should exist before the budget, because the budget is entered against them. The contract value and the rate template can be set at any point, but any hours recorded before a rate template is assigned will not carry a dollar value until it is.
Can I do this on a project that is already running?
Yes. All four settings can be changed on an active project. Be aware that changing a rate template affects how hours are costed going forward, so confirm with whoever owns the job costing before changing rates mid-project.
My report shows costs but no margin.
The Contract Value is almost certainly blank. Margin is calculated against it, so with no contract value there is no revenue figure to measure against. See Enter the Project Contract Value.
Labor hours are showing with no dollar value.
The project has no rate template assigned, or the labor class used on the Daily Report is not present on the assigned template. Check the Craft Template field on Project Info first, since an unassigned template is the more common cause. See Set the Project Rate Template.
The budget changed after we started. Do I edit it?
Not by hand. Budget adjustments should flow through Change Order Requests so the original budget, the approved changes and the revised total all remain visible and auditable. Editing the original budget directly erases the record of what changed and why.